Project:Top of the Marina Hotel
City: Herzliya
Contractor: Denya building Israel
The purpose of the project: Building Hotel
Culture and leisure hotel on Herzliya beach in the marina
The hotel will belong to the Fatal company, when it will include 327 rooms with 109 suite rooms.
Started in 2024 – will be completed by 2026.
It is built in 2 parts:
Part A – the higher part of the project Part B – the lower part.
In the project there is one floor of the 1st floor basement – for which they chose the POST&BEAM system for casting walls of variable thickness.
What made the project planning more complex?
As part of the design of the hotel, there will be inclined columns in the upper part of the hotel, and the Alumite design department specially adapted the Alumax mold system to them so that they can be cast and adapted to the performance requirement.
We at Alumlitght will continue to provide full escort from A to Z, with the receipt of equipment, confirmation of its arrival and training until the stage where the project will be carried out in the correct, safest and best way so that it will be carried out with great success.